The reports

This is the reference for all seventeen reports. For each one: what a row is, the columns it ships with, the columns you can add from Display options → Columns, the figures in the totals strip, and what a row breakdown opens.

  • Manufacturing
  • Bill of materials
  • Sales
  • Inventory
  • The summaries

What your store built in the period, per item, with the work orders and build runs behind it.

One row per item, period and location.

Column What it is Shown by default
Item The finished good, subassembly or variant that was built Yes
Location The production location the run happened at Yes
Item type BOM, Subassembly or Variant Yes
Units built Units produced by build runs in the build direction Yes
Units reworked Units run again as rework Yes
Units disassembled Units taken apart again Yes
Net units Units built minus units disassembled. Rework is replacement, not new output, so it stays out Yes
Work orders How many work orders contributed Yes
Build runs How many build runs contributed Yes
Average per run Built plus rework, divided by the build-direction runs Yes

Totals strip: Units built · Build runs · Units reworked · Units disassembled · Items.

Breakdown: every build run behind the row, named by its work order and run id, with the units it contributed. A disassembly counts negative, so the lines sum to built plus rework minus disassembled.

What quality control approved, failed, scrapped and sent back for rework, per item.

One row per item and period.

Column What it is Shown by default
Item The finished good, subassembly or variant reviewed Yes
Item type BOM, Subassembly or Variant Yes
Approved Units the reviewer passed Yes
Failed Units the reviewer failed Yes
Scrapped Failed units the reviewer scrapped Yes
Sent to rework Failed units the reviewer sent back Yes
Scrap rate Scrapped as a share of what was reviewed Yes
Top failure category The failure category with the largest quantity on this row Yes
Reviews How many reviews contributed No

Voided reviews are excluded entirely, so a reversed build run’s approvals and failures leave the figures.

Totals strip: Approved · Failed · Scrapped · Sent to rework · Items.

Breakdown: the failure categories behind the row, with the units failed under each. A failure with no category reads Uncategorized.

Planned against actual cost for every completed work order, with the variance per unit.

One row per completed work order. Work orders in progress are not in this report.

Column Shown by default
Work order Yes
Completed Yes
Units completed Yes
Current planned cost Yes
Actual cost Yes
Actual cost per unit Yes
Variance Yes
Current planned material cost · Current planned subassembly cost · Current planned labour cost · Current planned overhead No
Actual material cost · Actual subassembly cost · Actual labour cost · Planned overhead retained in actual cost No

Variance is measured against the latest plan, not the plan as it stood when the work order was created: editing a material or a quantity recomputes the planned figure.

Units completed counts units built. Units a disassembly run took apart again are not counted, so Actual cost per unit divides the actual cost by what was really built. The variance compares that actual cost with the whole plan: a work order planned at 2 units for $10 each that built 1 and disassembled 1 reads $20 planned, $10 actual, −50 %. The plan still prices the second unit, and nothing was spent on it.

Planned labour is the labour the work order is planned with: the figure you typed on the work order if you set one, otherwise the labour worked out from the bills’ labour cost rates. Planned overhead is what remains of the planned total after materials, sub-assemblies and that labour.

A work order that recorded no consumption at all — a material-list-only one, for instance — reports no actual cost rather than zero, and its units leave the average.

Totals strip: Actual cost · Current planned cost · Average cost per unit · Units completed · Work orders.

Breakdown: the work order’s items, each with the units completed, the unit cost it was costed at, and the quantity scrapped.

What manufacturing picked, consumed and returned, per material and location.

One row per material, period and location.

Column What it is Shown by default
Material The material, subassembly or finished good consumed Yes
Location Where the movement happened Yes
Material type Material, Subassembly or BOM Yes
Picked Units picked for a run Yes
Consumed Units actually consumed, net of any reversal Yes
Returned Units returned to stock Yes
Cost at consumption What those units cost at the moment they moved Yes
Work orders How many work orders contributed Yes

This is the one report whose money is the cost at the moment of the event rather than today’s cost. A fully reversed run reads nothing consumed beside what it returned. Disassembly runs are not counted as consumption: taking a finished good apart uses up no materials, so neither the finished good it takes apart nor the components it puts back appear here. There is no scrap column here: scrapped units are Scrap and quality’s question.

Totals strip: Consumed · Consumption cost · Returned · Materials.

Breakdown: the work orders behind the row, each with what it consumed, picked and returned.

How long work orders took from creation to completion, and how many met their due date.

One row per completed work order.

Column What it is Shown by default
Work order The completed work order the row measures Yes
Created · Started · Completed · Due The work order’s own timestamps Yes
Lead time Creation to completion Yes
On time Whether completion fell on or before the due date Yes
Wait before start Creation to start No
Time in build Start to completion No
Units completed Units the work order finished No
In progress at period end How many work orders were still open when the period (or bucket) closed. Marked Estimate, because exactly where the boundary falls changes it. Only meaningful with a Group by No

On time compares calendar days in your store’s time zone on both sides, because a due date is a day and not an instant. A work order that is re-opened counts as work in progress again.

Totals strip: Work orders · Average lead time · On time · Units completed.

Breakdown: the work order’s lifecycle steps in order — Created, Marked ready, Started, Paused, Sent to quality control, Completed and the rest — with the time each one took.

All five read what your order executions demanded. Three of them also answer on the Sold basis; see Basis.

What orders demanded of each finished good, and how much of it came off the shelf.

One row per finished good, period and location. Two bases.

Column What it is Shown by default Basis
Finished good The finished good the orders demanded Yes Both
Location The location the execution resolved to Yes Both
Net units Demanded minus restored Yes Both
Orders (counted per bill) Distinct orders touching this bill Yes Both
Executions How many executions contributed No Executed only
Units demanded What orders asked for No Executed only
Units restored What refunds and cancellations put back No Executed only
From the shelf Units met from pre-assembled stock No Executed only
From components Units built out of components at order time No Executed only
Revenue The discounted total of the units sold, net of refunds and edits No Sold only

Totals strip (Executed): Net units · Units demanded · Units restored · From the shelf · Finished goods. Totals strip (Sold): Net units · Orders · Revenue · Finished goods.

Breakdown: the components one level below this bill — its subassemblies and materials — with what each was demanded for. Not available on the Sold basis.

What executions demanded of each subassembly, and whether it came off the shelf, out of components, or fell short.

One row per subassembly, period and location. Two bases.

Column What it is Shown by default Basis
Subassembly The subassembly the executions demanded Yes Both
Location The location the execution resolved to Yes Both
Demanded What executions asked for Yes Both
Parent finished goods How many bills demanded it Yes Both
Orders (counted per subassembly) Distinct orders touching this subassembly Yes Both
From the shelf Met from pre-assembled stock No Executed only
From components Built out of its own components No Executed only
Shortfall Demanded but met by neither No Executed only
Shelf-only executions How many executions found this subassembly limited to its pre-assembled stock — the Only consume pre-assembled setting No Executed only
Shelf share From the shelf as a share of demanded No Executed only

Totals strip (Executed): Demanded · From the shelf · From components · Shortfall · Subassemblies. Totals strip (Sold): Demanded · Parent finished goods · Orders · Subassemblies.

Breakdown: the finished goods this subassembly was demanded by, with the quantity each one demanded. Not available on the Sold basis.

What orders consumed of each material, what refunds put back, and what it is worth.

One row per material, period and location. Two bases.

Column What it is Shown by default Basis
Material The material the orders demanded Yes Both
Location The location the material was demanded at Yes Both
Net demand Demanded minus restored Yes Both
Orders (counted per material) Distinct orders touching this material Yes Both
Finished goods How many bills demanded it Yes Both
Unit cost The material’s cost per unit today Yes Both
Demand value Demanded quantity at today’s unit cost. Marked Estimate Yes Both
Demanded What executions asked for No Executed only
Restored What refunds and cancellations put back No Executed only

Demand value is priced at today’s cost, because the demand record stores quantities and not the price of the day. For what a consumption actually cost when it happened, read Manufacturing consumption.

Totals strip (Executed): Net demand · Demanded · Restored · Demand value · Materials. Totals strip (Sold): Net demand · Demand value · Orders · Materials.

Breakdown: the assemblies the material was pulled through, with the quantity each path carried. A material that hangs off the bill itself is reported under that bill. Not available on the Sold basis.

How much of what your store assembled came off the pre-assembled shelf instead of being built from components.

One row per assembly and period, where an assembly is a finished good or a subassembly at any depth. One basis. No Location column, though the location scope still decides which executions count.

Column What it is Shown by default
Assembly The bill or subassembly Yes
Assembly type BOM or Subassembly Yes
Demanded What executions asked for Yes
From the shelf Met from pre-assembled stock Yes
From components Built out of components Yes
Shelf share From the shelf as a share of demanded Yes
Shortfall Demanded but met by neither Yes

Totals strip: From the shelf · From components · Shortfall · Assemblies · Shelf share. The strip’s shelf share is the ratio over the whole period, not the average of the per-row shares, so a one-unit assembly does not weigh as much as a thousand-unit one.

Breakdown: the orders the assembly was pulled for, with what each demanded and how it was met.

How many order executions ran in each period, how many failed, and how long they took.

One row per period. It is the one report whose row is a stretch of time rather than a thing, so it opens grouped by week. It has no location control (one execution can touch several locations), no search box (there is no name in it) and no row breakdown — a stretch of time has no named parts to open.

Column What it is Shown by default
Period The week, day or month Yes
Executions Executions that ran Yes
Failed Executions that failed Yes
Nothing to build Executions that matched no bill at all Yes
Average processing time How long the app itself took Yes
Average time from order to done From the order notification arriving to the execution finishing Yes

Totals strip: Executions · Failed · Average processing time.

Both sales reports read a local copy of your Shopify orders. See Order sync.

Variants you sold in the period that have no bill of materials behind them. Variants you sell from finished stock are left out.

One row per variant and period. No location control: a variant with no bill consumes nothing anywhere. A variant marked as sold from finished stock (see Operating repairs) is left out of this report and of the Sales summary’s unmodelled units from the moment it is marked, with no new order sync.

Column Shown by default
Product Yes
SKU Yes
Units sold Yes
Orders Yes
Revenue Yes

This is the list of things you might want to model. Sorted by units sold, the top of it is where modelling pays off first.

Totals strip: Units sold · Revenue · Variants.

Breakdown: the orders this variant was sold on, with the units on each.

Orders that contain a finished good you model, and for which no bill of materials was ever executed.

One row per order, newest first. No location control, and no row breakdown.

Column What it is Shown by default
Order The order number. Selecting it opens the Historical Orders tool with that order already selected Yes
Created When the order was placed Yes
Modelled lines How many lines on it match a bill Yes
Units How many units those lines carry Yes
Status Never seen, or Received, not processed Yes

The two statuses mean different things:

  • Never seen. The app has no record of the order at all. Either it was placed before you installed the app, or its notification never arrived.
  • Received, not processed. The app received the order, but no bill of materials ran to completion for it: nothing on it matched a bill of materials at the time, or the run did not complete.

To take several at once, tick their rows and choose Replay selected, which opens the same tool with all of them loaded.

The report never replays anything itself. The Historical Orders tool checks each order first, tells you which ones it will skip and why, and asks you to confirm, because replaying an order consumes its components for real and cannot be undone.

Totals strip: Orders · Units.

The three On hand reports answer a different question from every other report. They do not ask what happened over a period; they ask what the stock you hold right now is worth. So they have no period control, no Group by, no chart and no location scope: each one reads your whole shop as it stands the moment you open the page, and opening it again tomorrow gives tomorrow’s answer. They have no row breakdown. Search, filters, columns, saved views and export work as on any other report, and export takes every row.

Each of the three shows a short note above the table saying what its figures leave out. Read it before you quote a number from the report.

What all three have in common:

  • Today’s costs. Every value uses today’s recipes and the costs held in the app’s cost fields right now. Change a material’s cost and the value changes the next time the report is opened.
  • No tax. Costs are used exactly as you entered them. Nothing is added or removed for sales tax or GST.
  • Reserved and safety stock units are not shown. Units held back for open orders or as safety stock are not in any column.
  • Work in progress is kept apart. Units picked into a build run that has not finished yet sit in their own In progress columns, valued at materials cost, and are never added to the stock value. The totals strip shows them as a separate figure.
  • Which rows appear. One row per item that has stock on hand, or units in progress or awaiting quality control. An item with a negative quantity is listed, so overselling is visible, but it counts as zero in the totals strip rather than subtracting from it.
  • Cost incomplete. A row reads Yes here when its value could not be fully worked out: a material in it has no cost, its recipe loops back on itself, or it nests more than ten levels deep. Add the filter Cost incomplete is Yes to find the rows to fix.

In the two assembly reports, labour is the cost of your Labour-kind additional costs and additional costs is the cost of your Overhead-kind ones. Each step of the value builds on the one before it: without labour, then with labour, then including additional costs.

What the finished goods on your pre-assembled shelf are worth right now, with and without labour.

One row per finished good.

Only the pre-assembled shelf is counted. The quantity your product shows in Shopify can include what you could still build from components, which is not stock you hold, so it appears in its own column, Published in Shopify, and is never valued. When several bills share one product variant, its shelf is valued once, on one of them, and Other bills for this variant counts the rest.

Column What it is Shown by default
Finished good The finished good on the shelf Yes
SKU Its SKU Yes
On hand Units on the pre-assembled shelf, across all your locations Yes
Published in Shopify The quantity Shopify showed for this product when the app last read it. Shown beside On hand so the two are read as different numbers. Never valued Yes
Materials per unit What the materials in one unit cost at today’s recipe, waste included, through every level of subassemblies Yes
Value without labour On hand times materials per unit Yes
Value with labour Value without labour plus the labour value Yes
Value including additional costs Value with labour plus the additional costs value Yes
In progress Units of this item picked into a build run that has not finished Yes
Work in progress value In progress at materials cost Yes
Awaiting quality control Units built and waiting for a quality-control review. Not valued and not in the totals Yes
Cost incomplete See above Yes
Quantity from Pre-assembled shelf, or Pre-assembled total where the shelf has no per-location stock No
Labour per unit · Additional costs per unit The two cost layers for one unit No
Labour value · Additional costs value Those layers times On hand No
Labour split unknown Yes when another finished good is used as a component of this one. That component is priced at its Shopify cost, which cannot be split into materials and labour No
Other bills for this variant How many other bills share this product variant and were not valued No

Totals strip: Finished goods · Without labour · With labour · Including additional costs · Work in progress, materials.

What the subassemblies on your pre-assembled shelf are worth right now, with and without labour.

One row per subassembly.

Only the pre-assembled shelf is counted. What a subassembly could still be built into from its components is not stock, so it is not in this report.

Column What it is Shown by default
Subassembly The subassembly on the shelf Yes
SKU Its SKU Yes
On hand Units on the pre-assembled shelf, across all your locations Yes
Materials per unit What the materials in one unit cost at today’s recipe, waste included, through every level of nesting Yes
Value without labour On hand times materials per unit Yes
Value with labour Value without labour plus the labour value Yes
Value including additional costs Value with labour plus the additional costs value Yes
In progress Units of this subassembly picked into a build run that has not finished Yes
Work in progress value In progress at materials cost Yes
Awaiting quality control Units built and waiting for a quality-control review. Not valued and not in the totals Yes
Cost incomplete See above Yes
Quantity from Pre-assembled shelf, or Pre-assembled total where the shelf has no per-location stock No
Labour per unit · Additional costs per unit The two cost layers for one unit No
Labour value · Additional costs value Those layers times On hand No

Totals strip: Subassemblies · Without labour · With labour · Including additional costs · Work in progress, materials.

What your materials, Shopify-linked and virtual, are worth at cost right now.

One row per material.

A Shopify-linked material counts the quantity Shopify reported the last time the app read it, for the whole shop. A virtual materialVirtual materialA material tracked entirely inside Assemblified — not a Shopify variant. Useful for shop-floor consumables (glue, packaging, labour units) where you need quantity tracking but don't want a Shopify product on your storefront.Read more → counts the app’s own stock across its locations, or its total where it has no per-location stock. Product variants that are finished goods are not materials and are left out. Materials have no labour, so there is one value: the stock value at cost.

Column What it is Shown by default
Material The material Yes
SKU Its SKU Yes
Material type Shopify-linked or Virtual Yes
On hand The quantity counted, as described above Yes
Unit The material’s unit Yes
Quantity from Shopify, Assemblified locations, or Assemblified total Yes
Unit cost The material’s cost per unit today Yes
Stock value On hand times unit cost Yes
In progress Units picked into a build run that has not finished Yes
Work in progress value In progress at unit cost Yes
Cost incomplete Yes when the material has no cost Yes
Locations differ from total Yes when a virtual material’s per-location stock does not add up to its stored total. The per-location figure is the one counted No
Marked as a finished good Yes when the material is still marked as a finished good although no bill uses its variant. It is counted as a material No

Totals strip: Materials · Stock value · Work in progress, materials.

Why doesn’t this match Shopify’s inventory value?

The two answer different questions, so they rarely agree:

  • Different costs. These reports value finished goods and subassemblies at today’s recipe and the costs held in the app, and materials at the cost held on the material in the app. Shopify uses the cost per item set on each product in Shopify.
  • Different finished-good quantities. Shopify values the quantity it shows for a product. For a finished good the app counts only the pre-assembled shelf, because the quantity in Shopify can include units that are not built yet.
  • Units set aside. Units reserved for open orders or held as safety stock are not shown here.
  • Stock Shopify never sees. Virtual materials and subassemblies are kept in the app and have no product in Shopify, so they are in these reports and not in Shopify’s.
  • Labour and additional costs. The assembly reports show values with labour and including additional costs, which Shopify has no figure for. Compare Shopify’s number with Value without labour, never with a total that includes labour.
  • Timing. Shopify-linked quantities are as the app last read them, so a change made in Shopify a moment ago may not be counted yet.

Can I see what my stock was worth last month?

No. Each report is a reading of right now, and nothing is stored between readings, so a past date cannot be reconstructed afterwards. To keep a month-end figure, open the report on the 1st of the month, or on the last day, and export it. The exported file is your record.

Both are scorecards: five figures for the period, and the same five for the period before it. They have no rows, so no Group by, no filters, no columns, no breakdown and no export.

Figure Where it comes from
Units built Build output
Scrap rate Scrap and quality
Cost per unit Cost per build
On time Throughput
Consumption cost Manufacturing consumption

Carries the period control and the location scope.

Figure Where it comes from
Net units sold Your orders, net of refunds and removed units
Revenue Your orders, net of refunds and edits
Orders Distinct orders with at least one line still sold
Unmodelled units Unmodelled sales
Orders without execution Orders without execution

Carries the period control only. There is no location scope: an order line has no location of its own, only its shipments do, and this scorecard counts the store.

  • Reading a report — the toolbar, charts, saved views and export.
  • Order sync — the copy of your Shopify orders the sales reports read.
  • Overview — the catalogue, the three families and the On hand reports.